The machine is used to install overhead lines and for complex laying of new catenaries, in which the contact wire and catenary are pulled at the same time. Alternatively, a contact wire can be changed. In one operation, the old contact wire is reeled up and the new contact wire laid with a predefined tension. Another possible use is for laying railway power cables with predefined tension.

Funktionsmerkmale

  • Complex laying and renewal of contact line installations
  • Installation of railway power systems
  • Renewal of older installations
  • Rationalization of working processes to minimize track possession times
Eine ZECK-Komplexverlegeeinheit auf dem Gleis. Eine ZECK-Komplexverlegeeinheit auf dem Gleis. Eine ZECK-Komplexverlegeeinheit auf dem Gleis. Eine ZECK-Komplexverlegeeinheit auf dem Gleis.

Technical specifications

Engine
Deutz BF 4M 2012
EU emission standard
5
Weight
17,800 kg (without rope drums)
Height above top of rail
4.650 mm (transport position)
Kraft am Spilltrieb (Spannkraft)
200 – 3.200 daN
Geschwindigkeit bei Abspulen (Verlegen)
0 bis 5 km/h (83 m/min)
Geschwindigkeit bei Aufspulen
0 bis 0,5 km/h (8,3 m/min)

Dimensions without truck

Length
18.400 mm
Width
3.000 mm
Height
3.435 mm